Expansion Update 3/13/2015

The Plattsburgh International Airport expansion is still in phase II. Work that has been completed during the previous period includes:

  • Structural Steel continues in Departure Terminal Area
  • Communications Tower foundation
  • Completed Conference Room conversion
  • Continued Removal of Clock Tower
  • Prepare new area for Rental Car counters 
Upcoming work will include:
  • Relocate Communications Tower
  • Structural Steel continues in Departure Terminal
  • Work on Inbound Baggage area
The runway view from the secured passenger waiting area will be temporarily blocked, as the windows will be covered to prevent any damage due to steel construction in the new departure terminal.
 
No airport operational impacts to be reported at this time.