Expansion Update 4/17/2015

The Plattsburgh International Airport expansion is still in phase II. Work that has been completed during the previous period includes:

  • Front of Terminal canopy removal
  • Continued Structural Steel work
  • Elevator foundation excavation and forms
  • Prep for mud slab for ticketing canopy support columns
Upcoming work will include:
 
  • Complete canopy removal
  • Elevator foundation departure terminal
  • Second floor deck pour
No airport operational impacts to be reported at this time.
 
Passengers please be aware that there will be ongoing construction to the entry area of the terminal. The double door entrance to the east side of the building may be blocked off this week; however, entry will still be possible through the west side. Walkways will be marked for use. 
 