Expansion Update 3/20/2015

The Plattsburgh International Airport expansion is still in phase II. Work that has been completed during the previous period includes:

  • Relocated Terminal Communications Tower
  • Structural Steel in Departure Terminal – ongoing
Upcoming work will include:
  • Utility Building Area – block work will begin in the next two weeks
  • East canopy and Seal Tower Removal
  • FIS foundation work
  • Foundation work in future bag claim area
No airport operational impacts to be reported at this time.
 
*Two lanes closest to the airport terminal entrance may be blocked off temporarily due to construction.  When passengers are entering they should notice these lanes are blocked and should remain in the outer two left lanes.
 
 