Expansion Update 4/3/2015

The Plattsburgh International Airport expansion is still in phase II. Work that has been completed during the previous period includes:

  • East canopy and Seal Tower removal near completion
  • Vestibule Foundation work
  • Continued Structural Steel work
  • Block Work in Outbound Baggage area
  • FIS Foundation Work, Sequence 1
  • Entrance area to terminal – steel tie in demo (former concession area)
Upcoming work will include:
 
  • Under-slab utilities to begin for New Departure Terminal and Outbound Baggage within next two weeks*
  • Stairwell slab work for New Departure Terminal *
  • Elevator foundation in the New Departure Terminal *
  • Cold form framing in New Departure Terminal
  • Utility Building area continued block work
  • Jet Bridge Foundation 1
*weather permitting
 
No airport operational impacts to be reported at this time.
 